PHOTOS & LINKS

The Dam Project

The Proposed Dam and Inundation:

The dam wall would be located at “Byrrill Lagoon ”which is Platypus habitat. It would be an earth & rock fill dam with the spillway height at 40 mts high, (contour level 125-130mts) and 50 mts wide.

The catchment area is 53 square km. There are 2 options for dam size. For the larger dam of 36,000ML the amount of land inundated is 400ha and for the smaller dam of 16,000ML 240ha would be flooded.

6 dwellings would be flooded, one of them council owned. The dam would affect 24 land owners. The dam does not just flood Byrrill Creek valley, but also Kunghurloo & parts of Mebbin Springs. Access roads to 19 people's property would be affected. Local knowledge portrays different statistics to that of the Council.

The road west to Tyalgum would be severed & due to terrain and cost, it probably would not be replaced. Many people who live on the Tyalgum end of Byrrill Creek would lose their access to Uki & Kyogle road. Access to Mebbin National Park would be via Tyalgum, or Cadell Rd, and the Camp ground would not be accessible, unless a bridge was built, which is highly unlikely.

Geology

Investigations in 1977 revealed rock types at the site consisting of interlayered gently  dipping  sandstone  and  near  horizontal  dolerite  sills.  Except  for  minor outcrops of dolerite in the creek bed, the site is covered with residual soils.   The abutments are characterised by deep weathering with the dolerites providing rock with any great strength.   High leakage conditions have been encountered in the proposed embankment foundations, particularly on the left abutment.  Construction rockfill materials would need to be imported from an outside quarry although earthfill would be available within the dam storage and spillway excavations.

The geologist's report concludes as follows:

“Byrrill Creek site has some severe geological problems, the main one being the  considerable  depth  of  weathering  on  each  abutment. The  resultant clayey soil  and  highly weathered  material  would  make  it  very  difficult  to design an effective or economical cut-off structure.  The deep weathering in each abutment also commits the site to a fully lined spillway.  An extensive program of grouting would be required to establish an effective grout curtain.”

 

 

BACKGROUND AND HISTORY OF THE PROPOSED BYRRILL CREEK DAM AREA

Timeline of Events & Background On Proposed Byrrill Creek Dam:

1977    Reconnaissance Engineering Geological Survey of NSW, & Dept Public Works NSW

1978    Geological Survey of NSW, Feasibility investigation on Byrrill & Doon Doon Site

1980-1982 Clarrie Hall dam built for Tweed Water Supply

1983- Caveats placed on affected land in Byrrill Creek from this date.

1986 -Council purchases Wades land (1,131ha) at back end of Byrrill Creek. Land leased to Ken Morrow for cattle adgistment.

1993- Joint NSW Forestry & Council Forestry Plantation on 230ha of the land. Maturity 25-30yrs

1998- 2000 Council plants an extra 107ha & 56 ha

2004- NSW Dept Commerce: Construction of Byrrill Creek Dam & Cost estimate for 16,000ML dam

2007- SMEC commissioned to investigate dam at Rocky Cutting, Eungella

2007-  Byrrill Creek Dam @ 16,300ML costed at $38.3 million. Tweed Shire Council implements studies for extra water supply.

2009 October- NSW Dept Works (designer of Clarrie Hall Dam) commissioned to look at a larger 40,000 ML dam at Byrrill creek with estimated cost initially @$51 million, & now @ $58.4 million

2009- The Tweed River Area Unregulated & Alluvial Draft Water Sharing Plan is released with a prohibition on dams in Byrrill Creek & the Mid Tweed River.

2009 October- Tweed Council puts in an amendment to the prohibition to allow for town water supply.

2009 December- March 2010- TSC begins Community Consultation process on 4 Selected Options for new Water Supply with CWG members. The majority of CWG members do not support Byrrill Dam due to environmental significance & prohibition within the Draft Water Plan.

2010  April- Community Working Group [CWG] report is released asking for an independent review of the councils Demand Management Strategy prior to implementing any of the water supply options.

2010  October 19th Tweed Shire Council votes on Water Supply Options. Byrrill Creek dam moved from 3rd option to !st option. Recision motion put foward by 3 councilors.

2010 November 1st extraordinary council meeting maintains Byrrill Creek as 1st option.

2010 December New Tweed River Area Unregulated & Alluvial Water Sharing Plan is due to be gazetted

 

Pre Approval Plan

WaterSupply Augmentation
BYRRILL CREEK PRELIMINARY PRE APPROVALS PLAN

Time estimate

Preliminary

estimate

Outcome from deliverable

Timing / Sceduling constraints

Concept Design for Augmented Water Supply

$400,000

Concept Design

Storage Concept Design

180 days

Improved understanding of dam size required (FSL) and moreaccurate cost estimates

Requires geotech, seismic, survey andhydrological studies

Project Infrastructure Concept Design

Improved understanding of road, bridge and infrastructurerelocations required and more accurate cost estimates

Requires FSL height and survey

Geological / Geotech Studies ? PrelimImmediate Start

90 days

Improved understanding of ground conditions??> influence concept design

immediate start

Seismic StudiesImmediate Start

60 days

Input to concept design

immediate start, requires geotech studies

Survey

90 days

Input to hydrology study and concept design

immediate start

Hydrology Studies ? transmission losses? initial enviro flow estimates

Immediate Start

90 days

Improved understanding of dam size required, efficiency ofoperation

??> influence concept design

requires direction from governmentagencies to develop possible prelim

enviro flow scenarios

Environmental  Assessment

$1,000,000

Legal & Planning AdviceImmediate Start

120 days

Improved understanding of likely planning, licensing andoperating legal and legislative issues

??> influence environmental studies approach, EP&A approval

path, EPBC requirements, may highlight "show?stopper" issues

immediate start

Environmental Flow Studies ? detailed

400 days

Improved understanding of environmental flow requirements??> influence neogitations with Govt Agencies

??> input to EIS, Final Hydrological study & Detailed Design

Long investigation period ? up to 2yrs ?over several seasonal (and potentially

annual) variations

Environmental Impact Assessment

250 days

Soils, Landform Stability and Erosion Hazard

Input to EIS

Terrestrial Ecology

Input to EIS??> define EPBC requirements

??> influence EP&A, Detailed design, may highlight "show

stopper" issues

Long investigation period ? poss 12 mnths? over several seasons

Aquatic Ecology

Input to EIS??> define EPBC requirements

??> influence EP&A, Detailed design, may highlight "show

stopper" issues

Long investigation period ? poss 12 mnths? over several seasons

Flora and EECs

Input to EIS??> define EPBC requirements

??> influence EP&A, Detailed design, may highlight "show

stopper" issues

Long investigation period ? poss 12 mnths? over several seasons

Cultural Heritage Study

120 days

Improved understanding of cultural heritage significance??> define compensatory costs

??> influence EP&A, Detailed design, may highlight "show

stopper" issues

Relatively short investigation,consultation and reporting periods

Noise and Vibration

understand construction issues

Water Quality (Surface and Groundwater)

?

Riverbed and Bank Stability, Sediment Transport

?

Groundwater, Surface Water and Extraction

?

Air Quality

understand construction issues

Traffic, Access and Amenity

understand construction issuesunderstand road closure issues

Waste and Resource Use

understand construction issues

Economic and Social Impacts

?

Visual and Aesthetic

?

Recreational

?

Energy and Greenhouse

understand construction issues

Climate Change

hydrology issues

Community Consultation

?

Cumulative Impacts and Benefits

?

Negotiations with Government Agencies

$150,000

NPWS ? Revocation of NP land (incl. Act of Parliament)Immediate start

300 days

determine process, stakeholders, contacts, and likely timeframe& compensation for revocation of NP land

Long negotiation period ? potentially overseveral years

Planning Approval Requirements

EIS requirements (initial contact)Immediate start

60 days

determine process, stakeholders, and studies required ? willassist define EIS brief

??> informal feedback on likelihood of success / "show stopper"

issues??

immediate start

Adaptive Management requirements (initial contact)Immediate start

90 days

determine process, stakeholders, and studies required ? willassist define EIS brief

??> informal feedback only??

??> estimate of likely ongoing costs??

immediate start

Water Sharing PlanImmediate start

negotiate with Water Minister, determine likely enviro flowrequirements

immediate start

Fisheries requirementsImmediate start

understand probable enviro flow regimes, fish passage,compensatory costs,

immediate start

EPBC approval

60 days

?

refer legal assessment

refer legal assessment

Pre?construction Licenses

$2,000,000

Development of documentation for additional approvals

250 days

?

Approvals: Water Supply (s90 WMAct 2000), Fisheries, NP

200 days

?

Bio?banking / Compensatory habitat (NPWS)

?

Land Acquisitions

$50,000

Acquisitions PlanImmediate start

120 days

Improve understanding of areas to be acquired, approaches tonegotiations, purchase costs, other compensation costs, identify

owners of most need, likely timings

??> reduces uncertainties felt by landholders

immediate start, but will require FSLheight to finalise

Negotiations and acquisitions

300 days

?

?

$3,600,000